ERCOT Generator Interconnection

How a solar, storage, or hybrid project moves from a RIOO-IS application to commercial operations on the Texas grid, and what that means for diligence, timelines, and risk.

⚠️
The Protocols and Planning Guide control. This page summarizes the ERCOT Resource Interconnection Handbook (v1.95) and Planning Guide Section 5. It is not a substitute for the ERCOT Protocols, Planning Guide, Operating Guides, or Other Binding Documents, which govern in any conflict. Official hub: ercot.com/services/rq/integration
Stage 1Interconnection Request → QSA
Stage 2Registration & Modeling
Stage 3Energize → Synchronize → Commission
Key insight

ERCOT is not a FERC-style queue

ERCOT's generation interconnection process is not a classic FERC Order No. 2003-style serial queue with network-upgrade cost allocation and deliverability rights. Underwriting assumptions from PJM, MISO, or CAISO need to be adjusted.

Not a FERC queue

Each project moves through the process on its own. Congestion and staff capacity can create queue-like crunch points, but there is no formal queue with position-based rights. The monthly Generator Interconnection Status (GIS) Report is where the public sees project status.

Connect and Manage

Generation is connected and then managed through real-time congestion management. FIS studies ensure reliability. They are not intended to ensure deliverability or freedom from curtailment.

Driveway vs highway

Interconnection studies cover the "driveway", meaning the facilities needed to connect safely. Broader system upgrades (the "highway") go through the Regional Planning Group (RPG) planning process, not the interconnection study.

HIGHWAY: broader transmission system upgrades Regional Planning Group (RPG) process · Protocol 3.11.4 Your project solar · storage · hybrid POI DRIVEWAY: reliability interconnection SSS → FIS → SGIA with the TSP Connected ≠ deliverable. Real-time congestion management can curtail output.
GIS
Generator Interconnection Status

A public monthly report of interconnection milestones and trends. It is not a study stage.

≠
FIS
Full Interconnection Study

The detailed, TSP-led study package that follows screening: steady-state, short-circuit, dynamic/transient stability, and facility study.

Which path?

Three different regimes

Planning Guide 5.2.1 applies to new or modified Generation Resources, ESRs, or SOGs of 1 MW or more. Aggregate nameplate decides large vs small. Large Loads follow a separate set of rules.

New or modified facility in ERCOT
Planning Guide §5
≥ 10 MW

Large generation

  • Studies: SSS → FIS → Reactive → QSA
  • Agreement: SGIA with the transmission TSP
  • Separate modification rules apply
  • This is the path shown in the main flowchart below
Planning Guide §5.4
< 10 MW

Small generation

  • No SSS/FIS package like large gen
  • TDSP System Impact Study
  • Fully executed DSP/TSP interconnection agreement (or attestation)
  • Financial security for distribution upgrades and operational-limitation confirmations
  • Then ERCOT Approval to Submit Model Information
Planning Guide §9
Large Load

Large Load interconnection

  • Separate regime: Large Load Interconnection or Modification (evolving Batch Zero process)
  • Certain loads also appear in the QSA
  • Not the same as the GIM generation path. Keep it on its own branch.
  • Co-located load at a hybrid site needs both lenses. ERCOT provides separate coordination templates for co-located loads under 75 MW.
Path modifiers: Modifications, affiliate aggregation at the same substation, and the optional Self-Limiting Facility (SLF) designation can change the path. An SLF is studied and sized using its MW Injection / Withdrawal limits instead of full nameplate. It follows the same GIM process, and the limits cannot be raised without a new GIM.
Main process · Large generation (≥10 MW)

From application to commercial operations

Click any step to see what happens there and which documents it needs. Colors show the handbook stages: Stage 1 Stage 2 Stage 3

Stage 1 Step 1: GIM / GINR application

What happens

The Interconnecting Entity submits a Generator Interconnection or Modification (GIM), often still called a GINR, through RIOO-IS. It pays the Generation Interconnection Fee and receives an INR ID (yrINRxxxx). ERCOT reviews completeness, typically within 10 Business Days. Proposed large-gen COD must be at least 15 months after submission (PG 5.2.2).

Key documents & artifacts
  • GIM/GINR application in RIOO-IS
  • Generation Interconnection Fee (ACH/credit card per Fee Schedule)
  • Lone Star Infrastructure Protection Act attestation (PG §8 Att. D)
  • INR number assignment

Stage 1 Step 2: Security Screening Study

What happens

ERCOT runs a high-level steady-state screening (power flow / transfer) for the proposed POI and MW. It shows how much of the proposed generation can operate alongside other known generation in the area before significant transmission additions may be needed. It also screens for SSR study needs and SSO risk. ERCOT is allowed 90 days and may waive the SSS at its discretion.

Key documents & artifacts
  • Security Screening Study report (posted to IE via RIOO)
  • SSR vulnerability indication / Credible Single Contingency radial-to-series-capacitor count

Stage 1 Step 3: Full Interconnection Study

What happens

Within 180 days of SSS results, the IE must request FIS (dates, proof of site control, FIS-level data, fees) or the GIM is considered withdrawn. ERCOT designates a lead TSP, and the kickoff starts a 60-day clock to agree on scope. FIS covers steady-state, short-circuit, dynamic/transient stability, and facility study. SSR is scoped alongside FIS but is not part of it.

Key documents & artifacts
  • FIS change request + Proof of Site Control
  • Resource Registration data at FIS level (dynamic models / model quality tests)
  • FIS Application Fee (ERCOT); FIS Scope / Study Agreement with TSP(s)
  • DOD Siting Clearinghouse declaration (PG §8 Att. C) where applicable
  • Reports: steady-state, short-circuit, dynamics, facility study; SSR study (separate)
  • Optional ERCOT Economic Study if Tx costs expected >$25M

Stage 1 Step 4: SGIA + NTP + security

What happens

After the final FIS elements are complete and posted, the IE and TSP may execute the SGIA. ERCOT is not a party. The SGIA generally must be signed within 180 days of FIS completion or the GIM may be cancelled. Notice to Proceed and financial security for interconnection facilities are the key commercial milestones.

Key documents & artifacts
  • SGIA (current form for SGIAs executed on/after Jan 1, 2026), or other public financially binding IA
  • TSP notice of Notice to Proceed + financial security
  • Semiannual Declaration of Resource Data Accuracy (PG §8 Att. A) once FIS requested

Stage 1 Step 5: Planning Guide 6.9

What happens

Meeting PG 6.9 (signed SGIA, NTP, financial security, air permits / water declarations as applicable, required data) qualifies the project for planning models, QSA eligibility, and the Protocol 16.5 operational-standards review.

Key documents & artifacts
  • Signed SGIA + NTP + financial security (or MOU/EC letter)
  • TCEQ air-permit documentation (or none required)
  • Declaration of Adequate Water Supplies (wind/PV/battery ESS exempt per Att. B)
  • Planning Model column data

Stage 1 Step 6: Reactive Study & Protocol 16.5

What happens

The IE completes the Reactive Study. ERCOT determines compliance with operational standards under Protocol 16.5 and has 90 days from PG 6.9 to do so. If SSR mitigation is required, it must be ready before Initial Synchronization.

Key documents & artifacts
  • Reactive Study
  • Protocol 16.5 Compliance with Operational Standards determination
  • SSR mitigation (if required)

Stage 1 Step 7: Quarterly Stability Assessment

What happens

The QSA determines whether a project is eligible for Initial Synchronization in a given quarter. Prerequisites are due by fixed calendar deadlines. Missing a deadline means the project cannot synchronize in that three-month window.

Key documents & artifacts
  • QSA inclusion prerequisites package
  • QSA checklist (ERCOT)

Stage 2 Step 8: Registration & Modeling

What happens

Register as a Resource Entity, complete RIOO resource data through Full Registration (targeted ~120 days before the desired PLD), and coordinate the Network Operations Model through the Production Load Date. Set up EPS meters, ESI IDs, and telemetry/ICCP with the QSE and TSP.

Key documents & artifacts
  • Market Participant Agreement; RE Application for Registration
  • Managed Capacity Declaration; citizenship/ownership attestations; CEGE/CEGS LSIPA reporting
  • Resource Registration Glossary data (Full Registration)
  • NOMCRs (TSP); EPS meter design / cutover; GENMAP verification; ICCP point list

Stage 3 Step 9: Part 1 · Energize

What happens

Part 1 of the New Generator Commissioning Checklist: energize the Resource Entity's equipment, coordinating with the TSP at the POI.

Key documents & artifacts
  • Commissioning Plan Template
  • New Generator Commissioning Checklist Part 1

Stage 3 Step 10: Part 2 · Sync → Part 3 · Commission

What happens

Part 2 is Initial Synchronization with the required performance tests. QSA, SSR (if required), and operational-standards compliance must be satisfied first. Part 3 is the Request to Commission a Resource, which leads to commercial operations and INR status 'Operational'.

Key documents & artifacts
  • Checklist Parts 2 and 3
  • Test artifacts: IRR curtailment, reactive capability, VSS, AVR, PFR, PSS (as applicable)
  • As-built dynamic models for IBRs prior to commissioning
  • Weather preparedness declarations when required
Tip: use arrow keys while a step is focused to move between steps.
SSS→ FIS→ SGIA + NTP→ PG 6.9→ QSA→ PLD→ Part 1→ Part 2→ Part 3
Handbook framing

The three official stages

The Resource Interconnection Handbook groups the process into three stages. Stage 1 holds most of the study and commercial work.

1
Stage 1

Interconnection Request Application → QSA

  • GIM/GINR in RIOO-IS, fee, INR ID
  • Security Screening Study (SSS)
  • FIS request, scope agreement, FIS studies
  • SGIA, Notice to Proceed, financial security
  • Planning Guide 6.9, Reactive Study, Protocol 16.5 review
  • Quarterly Stability Assessment (QSA)
2
Stage 2

Registration and Modeling

  • Register as Resource Entity (if not already)
  • RIOO resource data through Full Registration (handbook targets ~120 days before desired PLD)
  • Network Operations Model via Production Load Date (PLD)
  • EPS meters, ESI IDs, telemetry/ICCP with QSE and TSP
3
Stage 3

Energization, Synchronization & Commissioning

  • Part 1 Energization
  • Part 2 Initial Synchronization with performance tests
  • Part 3 Request to Commission a Resource (commercial operations)
  • QSA, SSR (if required), and operational standards must be satisfied before synchronization
Actor Stage 1 · Request → QSA Stage 2 · Registration & Modeling Stage 3 · Energize → Commission
IE / RE Submits GIM, fees, site control, FIS data; signs FIS Scope Agreement and SGIA; posts NTP + security; meets PG 6.9; completes Reactive Study RE registration, MPA, Full Registration data, Managed Capacity Declaration, attestations Commissioning Plan; submits Checklist Parts 1–3; as-built dynamic models (IBRs)
TSP / TDSP Lead TSP runs FIS elements (and SSR if required); designs interconnection facilities; executes SGIA; posts NTP/security to RIOO Submits NOMCRs; EPS metering design / cutover; POI telemetry Coordinates POI energization
ERCOT Completeness review; runs SSS; designates lead TSP; reviews FIS/SSR; Economic Study if >$25M; PG 6.9 and 16.5 review; runs QSA Network Operations Model build to PLD; GENMAP verification Approves energization, synchronization, and commissioning; INR status → Operational
QSE — ICCP point list, telemetry setup Takes part in commissioning tests and checklist; SCED telemetry; outage scheduling
Who does what

Key actors

IE

Interconnecting Entity

The developer or applicant. Starts the GIM in RIOO-IS, pays fees, provides site control and resource data, funds TSP studies, negotiates the SGIA, and drives milestones. May or may not become the eventual RE.

RE

Resource Entity

Registers with ERCOT and owns or controls the Generation Resource, ESR, and/or Load Resource. Responsible for registration data, telemetry coordination through the QSE, and commissioning checklist submittals.

QSE

Qualified Scheduling Entity

Represents the Resource in the market. Handles ICCP/SCED telemetry and outage scheduling, and takes part in commissioning tests and the checklist process.

TSP

TSP / TDSP

The lead TSP runs the FIS, designs and builds interconnection facilities, executes the SGIA, and submits NOMCRs, EPS metering, and POI telemetry. For distribution-connected projects, DSP feasibility and the IA are critical.

ERCOT

ERCOT Resource Integration

Accepts the GIM, runs the SSS, designates the lead TSP, reviews FIS/SSR, runs the Economic Study (>$25M), administers RIOO, enforces PG 6.9 and QSA gates, sets the model PLD, approves commissioning, and publishes the GIS report.

Also involved: PUCT (regulatory oversight, e.g. SGIA form updates; Power Generation Company registration may be required for REs) and RPG / planning stakeholders (a separate path for broader transmission upgrades).

Timing · sourced ranges only

How long does it take?

ERCOT's own overall guidance excludes construction and supply-chain delays. Actual timelines vary widely with TSP study load, restudies after design changes, equipment lead times, and QSA quarter gates.

Large generation ≥10 MW
18–30 months

Approximate overall process. Source: ERCOT interconnection process presentation (Fernandes), Oct 28, 2024. Excludes construction/supply delays.

Small generation <10 MW
8–12 months

Approximate overall process. Source: same ERCOT presentation (Fernandes), Oct 28, 2024. Excludes construction/supply delays.

Resource Interconnection Handbook, Appendix I: GIM tabular timeline

These are ranges, not guarantees. The bars use a 0–300 day scale and show durations only, not a cumulative schedule (steps can overlap).

075150225300 days
Acknowledge GIM applicationERCOT
1–10 Business Days
SSS (after complete application)ERCOT
10–90 days
Decision to pursue FIS after SSSIE
Up to 180 days
FIS scope agreementIE, ERCOT, TSP(s)
Up to 60 days
Perform FIS (after scope)TSP(s)
40–300 days
SSRTSP(s)
60–180 days
Study report reviewERCOT & TSP(s)
10–15 Business Days
Execute SGIA after FIS acceptanceIE & TSP
180 days
Range (calendar days) Maximum / deadline ("up to") Business Days

QSA synchronization eligibility calendar

Planning Guide 5.3.5 / Handbook. If you miss the prerequisite deadline, the project is not eligible to synchronize in that three-month window.

Desired Initial Synchronization quarterQSA prerequisites due byQSA completion target
Jan – MarPrior Aug 1End of October
Apr – JunPrior Nov 1End of January
Jul – SepPrior Feb 1End of April
Oct – DecPrior May 1End of July
Other sourced timing anchors: Proposed large-gen COD must be at least 15 months after application submission (PG 5.2.2). ERCOT has 90 days from PG 6.9 for the Protocol 16.5 operational-standards review. The handbook prefers that Initial Synchronization → Resource Commissioning happen within ~120 days; longer commissioning should be split across INRs. Phases with in-service dates more than 3 months apart should be separate interconnection requests (they may share a study).
For sponsors, lenders & tax-equity

Finance-relevant callouts

The points from the ERCOT process that most affect underwriting, diligence checklists, and closing conditions.

Revenue risk

No deliverability guarantee

Under Connect and Manage, FIS covers reliability only. It does not guarantee market deliverability. Being interconnected does not mean being deliverable.

Revenue risk

Congestion curtailment

Generation is managed through real-time congestion management. FIS is not intended to ensure freedom from curtailment. Model it in the revenue case.

Status risk

Inactive → cancellation

Inactive status can remove a project from planning models and GIS capacity tallies. Transmission-connected projects can sit Inactive for up to 5 years before ERCOT may cancel.

Deadline risk

Withdrawal / cancellation clocks

If FIS is not requested within 180 days of SSS results, the GIM is considered withdrawn. If the SGIA is not signed within 180 days of FIS completion, the GIM may be cancelled (exceptions exist).

Structuring

Hybrids need dual INRs

Submit separate GIM/INR applications for each technology type (e.g., a solar INR plus a battery INR). ERCOT/TSP may hold one FIS kickoff and may use one SGIA that references both INRs.

2026 change

New SGIA form

The new SGIA (Nov 6, 2025 form) applies to agreements executed on or after Jan 1, 2026. The pre-2026 form is only for amendments or restatements of earlier SGIAs (PUCT Project 58211).

2026 change

Interconnection cost reporting

Under PG 5.2.8.4, TSPs began reporting monthly interconnection costs in Jan 2026. ERCOT includes them in GIS reporting and will publish an annual report starting Apr 2027.

2026 change

SSO risk rule

Under PG 5.2.10, generators whose original SGIA is executed on or after Apr 1, 2026 face stricter radial-to-series-capacitor interconnection constraints.

Diligence

Confidentiality flips at FIS

Large-gen project details stay Protected Information until FIS is requested (or the IE waives). After that, public GIS visibility and RPG-related disclosures apply under PG 5.2.3.

Diligence

Key closing artifacts

Signed SGIA, TSP notice of NTP + financial security, and PG 6.9 status are the milestones that open planning-model and QSA eligibility. FIS posting also triggers the semiannual Declaration of Resource Data Accuracy.

Diligence

Network upgrade cost signal

If interconnection transmission costs are expected to exceed $25M, ERCOT may run an optional Economic Study. The FIS facility study includes design, milestones, and cost estimates.

Technical

IBR model quality

Ride-through, NOGRR245, and IEEE 2800-related data obligations continue through the project's life in RIOO. Model quality and as-built dynamic models matter most for solar and storage.

Reference

Glossary

AVR
Automatic Voltage Regulator
COD
Commercial Operations Date
DESR / DGR
Distribution Energy Storage Resource / Distribution Generation Resource
DSP / TSP / TDSP
Distribution / Transmission / Transmission & Distribution Service Provider
ESR
Energy Storage Resource
ESI ID
Electric Service Identifier
FIS
Full Interconnection Study: the detailed TSP-led study package after screening
GIM
Generator Interconnection or Modification (Planning Guide term)
GINR
Generation Interconnection or Change Request (legacy/common term; still used on ERCOT pages and RIOO)
GIS
Generator Interconnection Status: monthly public report. Not a study.
IA / SGIA
Interconnection Agreement / Standard Generation Interconnection Agreement
IBR / IRR
Inverter-Based Resource / Intermittent Renewable Resource
IE
Interconnecting Entity
INR
Interconnection Request (project ID: yrINRxxxx)
MIS
Market Information System
NOMCR
Network Operations Model Change Request
NTP
Notice to Proceed (to the TSP, with financial security)
PFR
Primary Frequency Response
PLD
Production Load Date: when the resource enters the Network Operations Model
POI / POIB
Point of Interconnection / Point of Interconnection Bus
PSS
Power System Stabilizer
QSA
Quarterly Stability Assessment
QSE
Qualified Scheduling Entity
RARF
Resource Asset Registration Form (legacy term; data now largely entered in RIOO)
RE
Resource Entity
RIOO-IS / RIOO-RS
Resource Integration and Ongoing Operations: Interconnection Services / Resource Services
RPG
Regional Planning Group
SGIA
Standard Generation Interconnection Agreement
SLF
Self-Limiting Facility
SOG
Settlement Only Generator
SSO / SSR
Subsynchronous Oscillation / Subsynchronous Resonance
SSS
Security Screening Study
VSS
Voltage Support Service
Official ERCOT sources

Sources & deep links

Resource Integration hub (primary landing page) ↗[Resource Integration hub](https://www.ercot.com/services/rq/integration/) Resource Interconnection Handbook v1.95 (Oct 28, 2025) ↗[Resource Interconnection Handbook v1.95](https://www.ercot.com/files/docs/2021/01/07/Resource_Interconnection_Handbook_v1.95_10282025.docx) Current Planning Guide index ↗[Current Planning Guide index](https://www.ercot.com/mktrules/guides/planning/current) Planning Guide Section 5: Generator Interconnection or Modification (Aug 1, 2026) ↗[Planning Guide Section 5](https://www.ercot.com/files/docs/2025/12/01/05-080126.docx) Planning Guide Section 6 (incl. 6.9 Addition of Proposed Generation to Planning Models) ↗[Planning Guide Section 6](https://www.ercot.com/files/docs/2025/12/01/06-080126.docx) Planning Guide Section 9: Large Load Interconnection or Modification ↗[Planning Guide Section 9](https://www.ercot.com/files/docs/2011/04/28/09-071126.docx) SGIA (current; Nov 6, 2025 form, for SGIAs on/after Jan 1, 2026) ↗[SGIA](https://www.ercot.com/files/docs/2025/12/01/ERCOT-Standard-Generation-Interconnection-Agreement-Final-2025-11-06.docx) QSA checklist ↗[QSA checklist](https://www.ercot.com/files/docs/2025/10/28/QSA-checklist.docx) RIOO-IS / GINR portal entry ↗[RIOO-IS / GINR portal entry](https://sa.ercot.com/ginr/) Resource Adequacy / monthly GIS Report ↗[Resource Adequacy / monthly GIS Report](https://www.ercot.com/gridinfo/resource) GIS Report data product ↗[GIS Report data product](https://www.ercot.com/mp/data-products/data-product-details?id=pg7-200-er) Interconnection process overview (Fernandes, Oct 28, 2024) ↗[Interconnection process overview](https://www.ercot.com/files/docs/2024/10/30/0940-AM-ERCOT-Interconnection-Process-Generation-Entity-Winter-Weather-Preparedness-Fernandes.pdf) Distributed Generation / DGR page ↗[Distributed Generation / DGR page](https://www.ercot.com/services/rq/re/dgresource/) Resource Registration Glossary library ↗[Resource Registration Glossary library](https://www.ercot.com/mktrules/guides/resourcereg/library)

Useful handbook appendices (inside Handbook v1.95): D/E Large Gen Timelines · F/G Small Gen Timelines · H Small Gen Process Flowchart · I GIM Tabular Timeline. Process questions: [email protected]